Manufacturing mailing list archives

manufacturing@odoo-community.org

Avatar

Bill of Materials vs. WorkOrders

by
nagy.balage
- 17/07/2017 11:37:10
Dear All!

I would like to manage cutting of herbs with odoo, based on kg (volumes) and not on UNITS (quanties). The odoo work order insits on the BoM, however in real life the volumes produced of theese nature products vary. It would not be a serious problem but odoo does not allow me to „continue production“ (close a work order) until I produced everything.

In short: the quanities/volumes of the raw materials required for a manufacturing process vary most of the time.

Is such a thing doable with odoo?

Kind Regards

Balázs

Follow-Ups