ODOO11 MRP multiBom bad production planing
by
jeff
Hi,
I have a problem with mrp that I don't understand...
I have a product A, with a bom containing product B with routing R1
Product B has also a bom containing product C with routing R2.
Product C is a buyable product
if I confirm a Sale Order with product A, I have automatically 2 manufacture orders with R1 and R2.
But the problem is when I planify those MO, they start on the same date....
In reality, product B should be manufactured first and only then product A can be manufactured.
So in the Gantt view, we should have the MO planify with the proper order.
When I launch the planing, all manufacture order start at the same time...
Is there something I missed.
Thanks for your help it is a long time I'm searching ...
reagrds,Jeff